# The M25 Junction 28 Development Consent Order 2022, Paragraph 14: Operation of M25 Junction 28 Roundabout

Extent: E+W

(1) No part of the new loop road forming Work No. 6 is to be opened for traffic until a plan for the M25 Junction 28 roundabout containing details of the proposed operation of traffic signal timings or such other related measures as may be reasonably practicable to prevent any increase in delays for traffic on the A1023 Brook Street entering the M25 Junction 28 roundabout arising as a result of the authorised development has been submitted to and approved in writing by the Secretary of State, following consultation with the highway authorities within the Order limits.
(2) The authorised development must be operated in accordance with the approved plan referred to in sub-paragraph (1) or such amended plan following consultation with the highway authorities within the Order limits.

---
Source: https://www.legislation.gov.uk/uksi/2022/573/schedule/2/paragraph/14 (the official version)
Page: https://openlegislation.uk/m25-junction-28-development-consent-order-2022/schedule-2/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.