# The M25 Junction 28 Development Consent Order 2022, Paragraph 67

Extent: E+W

If in consequence of any agreement reached in accordance with paragraph 59(1) or the powers conferred by this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative rights and means of access to such apparatus as will enable Cadent to maintain or use the apparatus no less effectively than was possible before such obstruction.

---
Source: https://www.legislation.gov.uk/uksi/2022/573/schedule/9/paragraph/67 (the official version)
Page: https://openlegislation.uk/m25-junction-28-development-consent-order-2022/schedule-9/paragraph-67
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.