# The M3 Junction 9 Development Consent Order 2024, Paragraph 32: Arbitration

Extent: E+W

Save for differences or disputes arising under paragraphs 24(2) and(4) (removal of apparatus), 25(1) (facilities and rights for alternative apparatus)and paragraph 26 (retained apparatus: protection of SGN) any difference or dispute arising between the undertaker and SGN under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and SGN, be determined by arbitration in accordance with article 48 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2024/752/schedule/10/paragraph/32 (the official version)
Page: https://openlegislation.uk/m3-junction-9-development-consent-order-2024/schedule-10/paragraph-32/enacted
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.