# The M3 Junction 9 Development Consent Order 2024, Schedule 7: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Extent: E+W

(1)
Plot Reference Number shown on land plans
(2)
Purpose for which temporary possession may be taken
(3)
Relevant part of the authorised development
Land Plans – Sheet 4
4/1a
Land required temporarily for temporary traffic management purposes.
Ancillary works
4/1b
Required to facilitate and provide a working space and temporary access for works associated with the diversion of power cables.
Work No. 35
4/1c
Required to facilitate and provide a working space and temporary access for works associated with the construction of a new bridleway and associated drainage and landscaping features to connect Long Walk and Easton Lane.
Work No. 9
4/1d
Land required temporarily for temporary traffic management purposes.
Ancillary works
4/2a
Required to facilitate and provide a working space and temporary access for works associated with the diversion of 50 metres in length of power cables.
Work No. 35
4/2b
Required to facilitate and provide a working space and temporary access for works associated with the diversion of power cables.
Work No. 35
4/2c
Land required temporarily for temporary traffic management purposes.
Ancillary works
Land Plans – Sheet 5
5/5a
Requirement to facilitate and provide a working space and temporary access for works associated with the construction of a drainage outfall into the River Itchen.
Work No. 43
5/2d
Land required temporarily for temporary traffic management purposes.
Ancillary Works
5/2e
Required to facilitate and provide a working space and temporary access for works associated with:
1. the improvement and construction of the realignment of the northbound and southbound carriageways of the A33 between B3047 (London Road) / A33 junction and proposed A33 / M3 northbound onslip roundabout;
1(g). the construction of the extension of the existing central reserve with associated vehicle restraint system;
1(h). the construction of carriageway realignment on the existing River Itchen bridge (including possible remediation works);
3. the construction improvements and realignment of the southbound carriageway of the A34;
42. the construction of a drainage outfall into the River Itchen.
Work No. 1, 1(g), 1(h), 3, 42
5/3c
Required temporarily to facilitate construction generally and to facilitate and provide a working space and temporary access for works associated with the construction of a new bridleway and associated drainage and landscaping features to connect Long Walk to Easton Lane.
Work No. 9
5/4
Required temporarily to facilitate construction of surface water drainage outfall.
Work No. 42
Land Plans – Sheet 6
6/1f
Required to facilitate and provide a working space and temporary access for works associated with:
9. the construction of a new bridleway and associated drainage and landscaping features to connect Long Walk and Easton Lane;
9(a). the construction of an attenuation basin maintenance track;
20. the diversion of a low-pressure gas main pipeline;
26. the diversion of telecommunication equipment;
33. the realignment of the National Cycle Route 23 and associated earthworks and landscaping.
Work No. 9, 9(a), 20, 26, 33
6/1g
Required to construct a temporary construction site compound.
Work No. 38
6/4d
Required to facilitate and provide a working space and temporary access for works associated with the construction of a new bridleway and associated drainage and landscaping features to connect Long Walk to Easton Lane.
Work No. 9
6/6a
Required to facilitate and provide a working space and temporary access for works associated with the diversion of a low-pressure gas main pipeline.
Work No. 20
6/6b
Required to facilitate and provide a working space and temporary access for works associated with:
20. the diversion of a low-pressure gas main pipeline;
38: the construction of a temporary construction site compound situated on land to the east of the M3 Junction 9 gyratory.
Work Nos. 20, 38
Land Plans – Sheet 7
7/1a
Required to facilitate and provide a working space and temporary access for works associated with the construction of a temporary construction site compound situated on land to the east of the M3 Junction 9 gyratory.
Work No. 38
7/2c
Land required temporarily for temporary traffic management purposes.
Ancillary works
7/4g
Land required temporarily for temporary traffic management purposes.
Ancillary works
7/5
Land required temporarily for temporary traffic management purposes.
Ancillary works
7/6
Land required temporarily for temporary traffic management purposes
Ancillary works

---
Source: https://www.legislation.gov.uk/uksi/2024/752/schedule/7 (the official version)
Page: https://openlegislation.uk/m3-junction-9-development-consent-order-2024/schedule-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.