# The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016, Article 6: Power to deviate

Extent: E+W+S

In carrying out the scheduled works the undertaker may—
(a) deviate laterally from the lines or situations shown on the works plans within the Order limits in respect of any linear work and in respect of any non-linear work within the Non-linear Work Boundary for that work;
(b) deviate vertically from the levels shown or noted on the engineering drawings and sections, to a maximum of 0.5 metres upwards or downwards; and
(c) deviate vertically from the parapet heights stated on the engineering drawings and sections, to a maximum of 0.5 metres upwards.

---