# The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016, Paragraph 7: Environmental Management Plan

Extent: E+W+S

(1) No part of the authorised development is to commence until an EMP, substantially in accordance with the outline EMP (Application Document Reference No. 6.3, Appendix 4.2), has been submitted to and approved by the Secretary of State, following consultation with the relevant planning authority and the Environment Agency.
(2) All construction work must be carried out in accordance with the approved EMP unless otherwise approved by the Secretary of State, following consultation with the relevant planning authority and the Environment Agency.

---
Source: https://www.legislation.gov.uk/uksi/2016/863/schedule/2/paragraph/7 (the official version)
Page: https://openlegislation.uk/m4-motorway-junctions-3-to-12-smart-motorway-development-consent-order-2016/schedule-2/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.