# The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016, Paragraph 8: Construction Environmental Management Plan

Extent: E+W+S

(1) No part of the authorised development is to commence until a CEMP, substantially in accordance with the outline CEMP (Application Document Reference No. 6.3, Appendix 4.2A), annexed to the outline EMP (Application Document Reference No. 6.3, Appendix 4.2) has been submitted to and approved by the Secretary of State, following consultation with the Environment Agency and the relevant planning authority.
(2) The construction of the authorised development must be carried out in accordance with the CEMP.
(3) Upon completion of construction of the authorised development the CEMP must be converted into the HEMP.
(4) The authorised development must be operated and maintained in accordance with the HEMP.

---
Source: https://www.legislation.gov.uk/uksi/2016/863/schedule/2/paragraph/8 (the official version)
Page: https://openlegislation.uk/m4-motorway-junctions-3-to-12-smart-motorway-development-consent-order-2016/schedule-2/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.