# The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016, Schedule 7: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Extent: E+W+S

(1)
Location
(2)
Plot reference number(s) shown on Land Plans
(3)
Purpose for which temporary possession may be taken
(4)
Relevant part of the authorised development
Land Plans - Sheet 2
Section 1. District of West Berkshire
02–16, 02–17, 02–18
At railway level: temporary land required for access for inspection and possible refurbishment of bridge
1a, 1b, 2a, 2b
Section 1. District of West Berkshire
02–02a, 02–05
Land within existing highway boundary used for access to Scheme construction site and construction compound including traffic management
All works within Schedule 1
Section 1. District of West Berkshire
02–20, 02–20a, 02–20b, 02–22, 02–22a, 02–22b, 02–23, 02–23a, 02–23b, 02–25, 02–25a, 02–25b
At river and river bank level: temporary use for inspection and possible refurbishment of bridge
1a, 1b
Section 1. District of West Berkshire
02–08, 02–12
Temporary land required for use as construction compound
All works within Schedule 1
Section 1. District of West Berkshire
02–09, 02–10, 02–11
Temporary land required for use for access to construction compound
All works within Schedule 1
Land Plans - Sheet 3
Section 1. District of West Berkshire
03–07, 03–12
Temporary use for improvement and realignment of sliproads including traffic management and cross carriageway ducting
3a, 3b, 3c, 3d
Land Plans - Sheet 4
Section 1. District of West Berkshire
04–06, 04–08, 04–10
At railway level: temporary land required for access for inspection and possible refurbishment of bridge
1a, 1b
Section 1. District of West Berkshire
04–03, 04–04
Temporary use for inspection and possible refurbishment of culvert
1a, 1b
Land Plans - Sheet 6
Section 3. Borough of Reading
06–03, 06–04, 06–05, 06–08
Temporary traffic management and for access to Scheme construction site
All works within Schedule 1
Section 3. Borough of Reading
06–10, 06–10a, 06–12, 06–12a, 06–12b
Temporary traffic management, including lane restrictions, to create working space for construction of the Scheme including a gantry Type 1 and realignment of Junction 11 Eastbound on slip
1a, 4b
Section 2. Borough of Wokingham
06–09b, 06–10b, 06–13, 06–14, 06–14a, 06–14b, 06–20
Temporary traffic management, including lane restrictions, to create working space for construction of the Scheme including a gantry Type 1 and realignment of Junction 11 Eastbound on slip
1a, 4b
Land Plans - Sheet 7
Section 2. Borough of Wokingham
07–04, 07–05, 07–06, 07–08
Temporary use to create working space for construction of improved access to Cutbush Lane transmission station
1a
Section 2. Borough of Wokingham
07–11
Temporary use to create working space for removal of existing police observation platform
1a
Land Plans - Sheet 10
Section 2. Borough of Wokingham
10–07, 10–08, 10–09
At railway level: temporary use for inspection and possible refurbishment of bridge
1a, 1b, 5a
Land Plans - Sheet 17
Section 4. Royal Borough of Windsor and Maidenhead
17–12
Temporary use as construction compound
All works within Schedule 1
Land Plans - Sheet 18
Section 4. Royal Borough of Windsor and Maidenhead
18–02, 18–03
Temporary use as construction compound
All works within Schedule 1
Section 4. Royal Borough of Windsor and Maidenhead
18–07, 18–08
Temporary land required for access and working space to construct realigned Ascot Road and new Ascot Road overbridge including retaining wall to east side of Ascot Road
7a, 7b
Section 4. Royal Borough of Windsor and Maidenhead
18–09, 18–10, 18–17, 18–17a, 18–17b, 18–19
Temporary land required for access and working space to construct realigned Ascot Road and new Ascot Road overbridge
7a
Land Plans - Sheet 19
Section 4. Royal Borough of Windsor and Maidenhead
19–19, 19–19b, 19–20, 19–20a, 19–25, 19–27, 19–28a, 19–30, 19–30a, 19–33, 19–33a
At river and river bank level: temporary land required for widening Thames Bray underbridge
1a, 1b, 9a, 9b
Section 6. County of Buckinghamshire, District of South Bucks
19–35, 19–35a, 19–37, 19–37a, 19–38, 19–39
At river and river bank level: temporary land required for widening Thames Bray underbridge
1a, 1b, 9a, 9b
Section 4. Royal Borough of Windsor and Maidenhead
19-02, 19-02a, 19-02b, 19-06, 19-10
Temporary land required for access and working space for online reconstruction of Monkey Island Lane and Monkey Island Lane overbridge
8c
Section 4. Royal Borough of Windsor and Maidenhead
19–11, 19-14
Temporary land required for access and working space for online reconstruction of Monkey Island Lane and Monkey Island Lane overbridge and for widening of Thames Bray underbridge, including widening of the M4 and M4 embankment
8a, 8b, 8c, 9b
Section 6. County of Buckinghamshire, District of South Bucks
19-34, 19-36, 19-40, 19-41, 19-45, 19-46, 19-47, 19-49, 19-51, 19-53, 19-54, 19-55
Temporary land for access and working space for widening of Thames Bray underbridge to the North, including widening of the M4 and M4 embankment
9a, 9b
Section 4. Royal Borough of Windsor and Maidenhead
19-11a, 19-14a, 19-16, 19-18, 19-28, 19-29, 19-21, 19-22, 19-23, 19-24, 19-26, 19-31, 19-32
Temporary land for access and working space for widening of Thames Bray underbridge to the North, including widening of the M4 and M4 embankment
8a, 8b, 9a, 9b
Section 6. County of Buckinghamshire, District of South Bucks
19–56, 19–57, 19–57a
Temporary land for access and working space for widening the M4 and M4 embankment
10b
Section 6. County of Buckinghamshire, District of South Bucks
19-58, 19–59, 19–61, 19–62, 19–65, 19–73, 19–75, 19–76, 19–77, 19–79
Temporary land required for access and working space for online reconstruction of Marsh Lane and Marsh Lane overbridge
10c
Section 6. County of Buckinghamshire, District of South Bucks
19–80
At river level: temporary land required for access for inspection and possible refurbishment work to Jubilee River Bridge
1a, 1b
Land Plans - Sheet 20
Section 6. County of Buckinghamshire, District of South Bucks
20–02, 20–03, 20–03a, 20–07, 20–08, 20–09, 20–10, 20–12, 20–17, 20–20
Temporary land required for access and working space to construct realigned Lake End Road and new Lake End Road overbridge
11a, 11b, 11c
Section 7. Borough of Slough
20–27, 20–28
Temporary land required for access and working space to construct realigned Huntercombe Spur and new Huntercombe Spur overbridge
12b, 12e, 12f
Section 6. County of Buckinghamshire, District of South Bucks
20–22,
Temporary land required for access and working space to construct realigned Huntercombe Spur and new Huntercombe Spur overbridge
12b, 12c, 12d, 12e
Section 7. Borough of Slough
20–30, 20–31, 20–32, 20–32a, 20–33, 20–34, 20–35, 20–36, 20–37, 20–37a, 20–37b, 20–37c, 20–38, 20–41b, 20–41c
Temporary land required for access and working space for online reconstruction of Oldway Lane and Oldway Lane overbridge
13, 13b, 13c
Section 7. Borough of Slough
20–41, 20–41a
Temporary land required to enable temporary diversion of Rights of Way between Oldway Lane and Wood Lane
13c, 14c
Land Plans - Sheet 21
Section 7. Borough of Slough
21–01, 21–02, 21–02a
Temporary land required to enable temporary diversion of Rights of Way between Oldway Lane and Wood Lane
13c, 14c
Section 7. Borough of Slough
21–02b, 21–02c
Temporary land required to enable temporary diversion of Rights of Way between Oldway Lane and Wood Lane and for access and working space to construct and realign Wood Lane and new Wood Lane overbridge
13a, 13c, 14a, 14c
Section 7. Borough of Slough
21–02d, 21–04, 21–05, 21–06, 21–07, 21–12a, 21–13, 21–14, 21–15, 21–16, 21–17, 21–18
Temporary land required for access and working space to construct realigned Wood Lane and new Wood Lane overbridge
14a, 14b, 14c
Section 7. Borough of Slough
21–20, 21–21
Temporary land required for access and working space for the extension of Chalvey Culvert
15
Land Plans - Sheet 22
Section 7. Borough of Slough
22–22, 22–23, 22–24, 22–25
At railway level: temporary land required for access and working space for widening Windsor Branch railway underbridge to the South, including realignment of M4 and Junction 6 Westbound off-slip and embankment strengthening and widening
1a, 1b, 16b, 16c, 17
Section 7. Borough of Slough
22–01
Temporary access for inspection and possible refurbishment of culvert
1a, 1b
Section 4. Royal Borough of Windsor and Maidenhead
22–10
Temporary use for access to construction compound
All works within Schedule 1
Section 7. Borough of Slough
22–09
Temporary use for access to construction compound and to Scheme construction site
All works within Schedule 1
Section 4. Royal Borough of Windsor and Maidenhead
22–11
Temporary use as construction compound
All works within Schedule 1
Section 7. Borough of Slough
22–12, 22–26
Temporary land required for access and working space for widening Windsor Branch Railway underbridge to the South, including realignment of M4 and Junction 6 Westbound off-slip and embankment strengthening and widening
1b, 16c, 17
Section 7. Borough of Slough
22–18, 22–21
Temporary land required for access and working space for widening Windsor Branch Railway underbridge to the South, including realignment of M4 and Junction 6 Eastbound on-slip
1a, 16b, 17
Land Plans - Sheet 23
Section 7. Borough of Slough
23–02, 23–03, 23–04
Temporary land for access and working space to extend Water Main and Gas Main subway
18
Section 4. Royal Borough of Windsor and Maidenhead
23–12
Temporary land required for access and working space to construct realigned Datchet Road and new Datchet Road overbridge
19a, 19c
Section 7. Borough of Slough
23–11
Temporary land required for access and working space to construct realigned Datchet Road and new Datchet Road overbridge
19a, 19c
Section 7. Borough of Slough
23–07, 23–08
Temporary land for possible realignment of private means of access to Datchet Road
19c
Section 4. Royal Borough of Windsor and Maidenhead
23–32
Temporary land required for access and working space for online reconstruction of Recreation Ground overbridge
20a, 20c
Section 7. Borough of Slough
23–33
Temporary land required for access to finishing works on Recreation Ground road and Recreation Ground overbridge
20c
Section 4. Royal Borough of Windsor and Maidenhead
23–34, 23–35
Temporary land required for access and working space to extend Water Main subway
21
Section 4. Royal Borough of Windsor and Maidenhead
23–29
Temporary use as construction compound and temporary land required for access and working space to construct realigned Datchet Road and new Datchet Road overbridge, and temporary land required for access and working space for online reconstruction of Recreation Ground overbridge
19c, 20c, All works within Schedule 1
Section 7. Borough of Slough
23–19
Temporary use as construction compound and temporary land required for access and working space to construct realigned Datchet Road and new Datchet Road overbridge
19c, All works within Schedule 1
Land Plans - Sheet 24
Section 4. Royal Borough of Windsor and Maidenhead
24-02, 24-03, 24-04, 24-05, 24-06, 24-07, 24-08, 24-09, 24-10, 24-11, 24-12, 24-13, 24-14, 24-15, 24-16, 24-17, 24-18, 24-20, 24-21, 24-22, 24-23, 24-24, 24-25, 24-29, 24-30, 24-32, 24-33, 24-34a
Temporary land required for access and working space to construct realigned Riding Court Road and new Riding Court Road overbridge
22a, 22b, 22c
Section 4. Royal Borough of Windsor and Maidenhead
24-34, 24-36, 24-40
Temporary traffic management, including lane restrictions on Riding Court Road, to create working space for construction of the Scheme
1a, 23a, 23b
Section 4. Royal Borough of Windsor and Maidenhead
24-37, 24-38
Temporary traffic management, including lane restrictions on Majors Farm Road, to create working space for construction of the Scheme
1b
Land Plans - Sheet 25
Section 4. Royal Borough of Windsor and Maidenhead
25-01, 25-02
Temporary traffic management, including lane restrictions on Riding Court Road, to create working space for construction of the Scheme
1a, 24a
Section 7. Borough of Slough
25-03, 25-06, 25-09
Temporary traffic management, including lane restrictions on Riding Court Road, to create working space for construction of the Scheme
1a, 24a
Section 4. Royal Borough of Windsor and Maidenhead
25-11
Temporary traffic management, including lane restrictions on Majors Farm Road, to create working space for construction of the Scheme
1b, 24d
Section 7. Borough of Slough
25-15, 25-19
Temporary traffic management, including lane restrictions on Majors Farm Road, to create working space for construction of the Scheme
1b, 24d
Section 7. Borough of Slough
25-20, 25-22
Temporary traffic management and access to Scheme construction site
All works within Schedule 1
Section 7. Borough of Slough
25-30, 25-31, 25-32, 25-33, 25-34
Temporary use as construction compound
All works within Schedule 1
Land Plans - Sheet 26
Section 7. Borough of Slough
26-03, 26-06, 26-09, 26-10, 26-19
Temporary land required for access and working space for online reconstruction of Old Slade Lane and Old Slade Lane overbridge
25, 26a, 26b
Section 6. County of Buckinghamshire, District of South Bucks
26-02, 26-18
Temporary land required for access and working space for online reconstruction of Old Slade Lane and Old Slade Lane overbridge
25, 26a
Section 7. Borough of Slough
26-09a, 26-10a, 26-11, 26-12, 26-13
Possible temporary access or diversion route for Old Slade Lane
25
Land Plans - Sheet 27
Section 6. County of Buckinghamshire, District of South Buckinghamshire
27-12a, 27-12b, 27-12c, 27-12d, 27-12e, 27-12f
At motorway level; land within existing motorway boundaries retained for construction and operation of the Scheme. At railway level: temporary access for inspection and possible refurbishment of the bridge.
1a, 1b, 27a, 27b
Section 7, Borough of Slough
27-13a, 27-13b, 27-13c, 27-13d
At motorway level; land within existing motorway boundaries retained for construction and operation of the Scheme. At railway level: temporary access for inspection and possible refurbishment of the bridge.
1a, 1b, 26a, 26b
Land Plans - Sheet 28
Section 8. London Borough of Hillingdon
28-04, 28-05, 28-06, 28-07, 28-09, 28-10, 28-11, 28-12
Temporary access and working space for extension of Sipson Road subway
28, 29a, 29d
Land Plans - Sheet 29
Section 8. London Borough of Hillingdon
29-01, 29-02, 29-03
Temporary use as construction compound
All works within Schedule 1
Land Plans - Sheet 30
Section 8. London Borough of Hillingdon
30-03
For inspection and possible refurbishment to St Dunstans Subway
1a,1b

---
Source: https://www.legislation.gov.uk/uksi/2016/863/schedule/7 (the official version)
Page: https://openlegislation.uk/m4-motorway-junctions-3-to-12-smart-motorway-development-consent-order-2016/schedule-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.