# The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016, Paragraph 26

Extent: E+W+S

(1) The undertaker must—
(a) at all times afford reasonable facilities to the engineer for access to a specified work or protective work during its construction; and
(b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or protective work or the method of constructing it.

---
Source: https://www.legislation.gov.uk/uksi/2016/863/schedule/9/paragraph/26 (the official version)
Page: https://openlegislation.uk/m4-motorway-junctions-3-to-12-smart-motorway-development-consent-order-2016/schedule-9/paragraph-26
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.