# The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016, Paragraph 67: Expenses and costs

Extent: E+W+S

(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of the authorised development or any such works referred to in paragraphs 61, 63(2), or 65(1), or by reason of any subsidence resulting from such development or works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of a protected person, or there is any interruption in any service provided or of any access to any apparatus, or in the supply of any goods, by any protected person, the undertaker must—
(a) bear and pay the cost reasonably incurred by that protected person in making good such damage or restoring the supply;
(b) make reasonable compensation to that protected person for any other expenses, loss, damages, penalty or costs incurred by the protected person, by reason or in consequence of any such damage or interruption; and
(c) make reasonable compensation to that protected person in respect of any claim or demand made by a third party in respect of any damage by reason or in consequence of the construction of the authorised development or any such works referred to in paragraphs 61, 63(2), or 65(1).
(2) The fact that any act or thing may have been done by a protected person on behalf of the undertaker or in accordance with a plan approved by a protected person or in accordance with any requirement of a protected person or under its supervision does not, subject to sub-paragraph (3), excuse the undertaker from liability under the provisions of sub-paragraph (1).
(3) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of a protected person, its officers, servants, contractors or agents.
(4) A protected person must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made without the consent of the undertaker such consent not to be unreasonably withheld or delayed.

---
Source: https://www.legislation.gov.uk/uksi/2016/863/schedule/9/paragraph/67 (the official version)
Page: https://openlegislation.uk/m4-motorway-junctions-3-to-12-smart-motorway-development-consent-order-2016/schedule-9/paragraph-67
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.