# The M5 Junction 10 Development Consent Order 2025, Paragraph 12: Surface water drainage

Extent: E+W

(1) No part of the authorised development is to commence until written details of the surface water drainage system for that part, in accordance with the mitigation measures in chapter 8 (road drainage and the water environment) of the environmental statement and including means of pollution control, have been submitted to and approved in writing by the relevant planning authority following consultation with the county planning authority, the strategic highway authority and the Environment Agency.
(2) The drainage system must be constructed in accordance with the approved details referred to in sub-paragraph (1) unless otherwise agreed in writing by the relevant planning authority following consultation with the county planning authority, strategic highway authority and the Environment Agency.

---
Source: https://www.legislation.gov.uk/uksi/2025/795/schedule/2/paragraph/12 (the official version)
Page: https://openlegislation.uk/m5-junction-10-development-consent-order-2025/schedule-2/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.