# The M54 to M6 Link Road Development Consent Order 2022, Paragraph 32: Arbitration


Save for differences or disputes arising under paragraph 24(2) and (4) (removal of apparatus) and 26(11) (retained apparatus: protection of Cadent) any difference or dispute arising between the undertaker and Cadent under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and Cadent, be determined by arbitration in accordance with article 42 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2022/475/schedule/9/paragraph/32 (the official version)
Page: https://openlegislation.uk/m54-to-m6-link-road-development-consent-order-2022/schedule-9/paragraph-32
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.