# The M60/M62/M66 Simister Island Interchange Development Consent Order 2025, Paragraph 12: Footpath passing through Haweswater underpass

Extent: E+W

(1) No part of Work Nos. 5, 6, 7, 8, 10 and 11 is to commence until a scheme detailing improvements to the path passing through Haweswater underpass has been submitted to and approved in writing by the Secretary of State following consultation with the relevant planning authority and any statutory undertaker whose apparatus may be impacted by any proposed improvements.
(2) The scheme prepared under sub-paragraph (1) must incorporate details of improvements to the path within the Order land between Heybrook Close and Parrenthorn Road which passes through the underpass, details of any lighting, a timescale for implementation and details of future maintenance.
(3) The scheme approved under sub-paragraph (1) must be implemented in accordance with the approved details prior to bringing into use Work Nos. 5, 6, 7, 8, 10 and 11 and thereafter must be retained for the life of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2025/1018/schedule/2/paragraph/12 (the official version)
Page: https://openlegislation.uk/m60m62m66-simister-island-interchange-development-consent-order-2025/schedule-2/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.