# The M60/M62/M66 Simister Island Interchange Development Consent Order 2025, Schedule 5: LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED

Extent: E+W

(1)
Plot Reference Number shown on Land Plans
(2)
Purpose for which rights and restrictive covenants over land may be acquired
(3)
Relevant part of the authorised development
Land Plans – Sheet 1
1/6b
Required to operate, access and maintain the authorised development.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 02
1/6c
Required to operate, access and maintain the authorised development.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 02
1/33b
Required to operate, access and maintain the authorised development.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 02
1/34
Required for maintenance and access for utilities diversions.
Rights to install, maintain and use ducts, cables and apparatus for utilities and electronic communications operators.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 50
Land Plans – Sheet 2
2/1at
Required to construct, operate, access and maintain the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work No. 35, 36, 37, and 38
2/1au
Required to construct, operate, access and maintain the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work No. 35, 36, 37, and 38
2/1ax
Required to construct, operate, access and maintain the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work No. 35, 36, 37, and 38
2/4b
Required to construct, operate, access and maintain environmental mitigation areas and the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work Nos. 31 and 32
2/4e
Required to construct, operate, access and maintain the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work No. 35, 36, 37, and 38
2/4f
Required to construct, operate, access and maintain the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work No. 35, 36, 37, and 38
2/4g
Required to construct, operate, access and maintain the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work No. 35, 36, 37, and 38
2/4h
Required to construct, operate, access and maintain the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work No. 35, 36, 37, and 38
2/4i
Required to construct, operate, access and maintain the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work No. 35, 36, 37, and 38
2/5d
Required for maintenance and access for utilities diversions.
Rights to install, maintain and use ducts, cables and apparatus for utilities and electronic communications operators.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 52
2/7c
Required for maintenance and access for utilities diversions.
Rights to install, maintain and use ducts, cables and apparatus for utilities and electronic communications operators.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 52
2/8c
Rights to install, maintain and use ducts, cables and apparatus for utilities and electronic communications operators.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 51
2/8d
Rights to install, maintain and use ducts, cables and apparatus for utilities and electronic communications operators.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 51
2/9
Required for maintenance and access for utilities diversions.
Rights to install, maintain and use ducts, cables and apparatus for utilities and electronic communications operators.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 52
2/10
Required for maintenance and access for utilities diversions.
Rights to install, maintain and use ducts, cables and apparatus for utilities and electronic communications operators.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 52
2/13a
Required to construct, operate, access and maintain environmental mitigation areas and the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work Nos. 31 and 32
2/13b
Required to construct, operate, access and maintain environmental mitigation areas and the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work Nos. 31 and 32
2/16c
Required to construct, operate, access and maintain the authorised development.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 37
2/16e
Required to construct, operate, access and maintain the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and mitigation features being removed or maintenance being made materially more difficult.
Work No. 35, 36, 37, and 38
Land Plans – Sheet 4
4/2b
Required to construct, operate, access and maintain utilities diversions including a water main and the authorised development.
Rights to install, maintain and use ducts, cables and apparatus for utilities and electronic communications operators.
Right to pass and repass with or without plant and vehicles and access highways.
To include restrictive covenants for protecting the installed apparatus from excavation and to prevent access to the installed apparatus being made materially more difficult.
Work No. 41
4/2c
Required to construct, operate, access and maintain attenuation and drainage features and the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and drainage features being removed or maintenance being made materially more difficult.
Work No. 43
4/3
Required to construct, operate, access and maintain attenuation and drainage features and the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and drainage features being removed or maintenance being made materially more difficult.
Work No. 43
4/6
Required to construct, operate, access and maintain attenuation and drainage features and the authorised development.
Rights to maintain and to pass and repass with or without plant and vehicles and access highways.
To include the imposition of restrictive covenants to prevent works and drainage features being removed or maintenance being made materially more difficult.
Work No. 43 and 44

---
Source: https://www.legislation.gov.uk/uksi/2025/1018/schedule/5 (the official version)
Page: https://openlegislation.uk/m60m62m66-simister-island-interchange-development-consent-order-2025/schedule-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.