# The Mallard Pass Solar Farm Order 2024, Paragraph 109: Arbitration

Extent: E+W

Save for paragraphs 101(2), 101(4), 102(1) and 103, any difference or dispute arising between the undertaker and Cadent under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and Cadent, be determined by arbitration in accordance with article 40 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2024/796/schedule/15/paragraph/109 (the official version)
Page: https://openlegislation.uk/mallard-pass-solar-farm-order-2024/schedule-15/paragraph-109
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.