  "url": "https://openlegislation.uk/mallard-pass-solar-farm-order-2024/schedule-15/paragraph-93",
  "json_url": "https://openlegislation.uk/mallard-pass-solar-farm-order-2024/schedule-15/paragraph-93.json",
  "legislation": "uksi/2024/796",
  "legislation_title": "The Mallard Pass Solar Farm Order 2024",
  "legislation_url": "https://openlegislation.uk/mallard-pass-solar-farm-order-2024",
  "path": "schedule/15/paragraph/93",
  "kind": "paragraph",
  "number": "93",
  "heading": null,
  "text": "The undertaker must, no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 39 (certification of plans and documents, etc.), provide a set of those certified plans to Network Rail in a format specified by Network Rail.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 15 para. 93 in force at 3.8.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/796/schedule/15/paragraph/93",
    "retrieved_at": "2026-10-28T21:28:01.809186+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}