# The Mallard Pass Solar Farm Order 2024, Paragraph 1: Interpretation

Extent: E+W

In this Schedule—
“both relevant planning authorities” means South Kesteven District Council and Rutland County Council each being the relevant planning authority for part of the authorised development;
“date of final commissioning” means in respect of each phase of the authorised development as approved under requirement 3 the date on which each phase of the authorised development commences operation by generating electricity on a commercial basis but excluding the generation of electricity during commissioning;
“decommissioning timing provisions” means provisions relating to the timing for decommissioning works to take place, being all of section 2.4 of the outline operational environmental management plan; and
“relevant highway authority” means the highway authority for the highways that are the subject of a construction traffic management plan submitted pursuant to requirement 13(1).

---
Source: https://www.legislation.gov.uk/uksi/2024/796/schedule/2/paragraph/1 (the official version)
Page: https://openlegislation.uk/mallard-pass-solar-farm-order-2024/schedule-2/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.