# The Mallard Pass Solar Farm Order 2024, Paragraph 12: Operational environmental management plan

Extent: E+W

(1) Prior to the date of final commissioning for any phase of the authorised development, an operational environmental management plan (which must be substantially in accordance with the outline operational environmental management plan and which must include the decommissioning timing provisions) for that phase must be submitted to and approved by the relevant planning authority for that phase or, where the phase falls within the administrative areas of both the District of South Kesteven and the County of Rutland, both relevant planning authorities, such approval to be in consultation with the Environment Agency and Lincolnshire County Council.
(2) The operational environmental management plan must include details of road routes to and from the site for any heavy goods vehicles required during operation.
(3) The operation of any phase of the authorised development must be carried out and maintained in accordance with the approved operational environmental management plan for that phase.

---
Source: https://www.legislation.gov.uk/uksi/2024/796/schedule/2/paragraph/12 (the official version)
Page: https://openlegislation.uk/mallard-pass-solar-farm-order-2024/schedule-2/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

