  "url": "https://openlegislation.uk/mallard-pass-solar-farm-order-2024/schedule-2/paragraph-3",
  "json_url": "https://openlegislation.uk/mallard-pass-solar-farm-order-2024/schedule-2/paragraph-3.json",
  "legislation": "uksi/2024/796",
  "legislation_title": "The Mallard Pass Solar Farm Order 2024",
  "legislation_url": "https://openlegislation.uk/mallard-pass-solar-farm-order-2024",
  "path": "schedule/2/paragraph/3",
  "kind": "paragraph",
  "number": "3",
  "heading": "Phasing of the authorised development and date of final commissioning",
  "text": "(1) No part of the authorised development may commence until a written scheme setting out the phase or phases of construction of the authorised development has been submitted to and approved by the relevant planning authorities.\n(2) The scheme submitted pursuant to sub-paragraph (1) must include a timetable for the construction of the phase or phases of the authorised development and a plan identifying the phasing areas.\n(3) The scheme submitted and approved pursuant to sub-paragraph (1) must be implemented as approved.\n(4) Notice of the date of final commissioning with respect to each phase of Work No. 1 must be given to the relevant planning authorities within 15 working days of the date of final commissioning for that phase.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 3 in force at 3.8.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/796/schedule/2/paragraph/3",
    "retrieved_at": "2026-10-28T21:28:01.809186+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}