# The Manston Airport Development Consent Order 2022, Paragraph 5

Extent: E+W+S

(1) No part of Work No. 19 is to commence until the detailed design for that Work and details of safety processes associated with operation of that Work have been submitted to and approved in writing by the relevant planning authority, following consultation with the Environment Agency.
(2) The details approved under sub-paragraph (1) must reflect the relevant actions and commitments set out in the register of environmental actions and commitments.
(3) The construction, maintenance and operation of Work No. 19 must be carried out in accordance with the details approved under sub-paragraph (1).

---