Part III WORKS
A harbour arm comprising—
a bund commencing at point E on the deposited plan (being a point 194 metres from the base of the existing lighthouse) by a junction with the existing quay wall of the harbour at its southern end, passing north-west for a distance of 82 metres to point F on the deposited plan, then passing in a northerly direction for a distance of 103 metres to point G on the deposited plan and there terminating;
a retaining wall commencing at point M (being a point 188 metres from the base of the existing lighthouse) on the deposited plan by a junction with the said quay wall, passing north-north-west for a distance of 100 metres to a point L on the deposited plan, then passing due north for a distance of 48 metres to point K on the deposited plan and there terminating;
a quay wall commencing at points G-K on the deposited plan by a junction with the bund and retaining wall, passing north-east for a distance of 70 metres to point J on the deposited plan and there terminating 83 metres north-east of the seaward end of the Stone Pier; and
a reclamation area between the bund and retaining wall within points E, F, G, K, L and M on the deposited plan.
- 9Power to construct, etc., works
- 10Power to make subsidiary works
- 11Power to deviate
- 12Power to dredge
- 13Fine for obstructing works
- 14Tidal works not to be executed without approval of Secretary of State
- 15Provision against danger to navigation
- 16Abatement of works abandoned or decayed
- 17Survey of tidal works
- 18Permanent lights on tidal work
- 19Lights on tidal works during construction