# The Margate Pier (Turner Centre) Order 2005, Schedule 3: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN


(1)
(2)
(3)
(4)
Location
Number and description of land shown on land plan
Purpose for which temporary possession may be taken
Authorised work
District of Thanet
No. 3. Part of the stone pier.
Temporary works area and access to works
Work Nos. 1A and 1B
District of Thanet
No. 4. Storage hut and part of the stone pier.
Temporary works area and access to works
Work Nos. 1A and 1B
District of Thanet
No. 5. Storage hut and part of the stone pier.
Temporary works area and access to works
Work Nos. 1A and 1B
District of Thanet
No. 6. Storage hut and part of the stone pier.
Temporary works area and access to works
Work Nos. 1A and 1B
District of Thanet
No. 7. Storage hut and part of the stone pier.
Temporary works area and access to works
Work Nos. 1A and 1B
District of Thanet
No. 8. Area of sea, fundus, foreshore and slipway to the south of Margate Pier.
Temporary works area
Work Nos. 1A, 1B and 2
District of Thanet
No. 9. Council office building (Droit House).
Temporary works area and access to works
Work Nos. 1A, 1B and 2
District of Thanet
No. 11. Car and Coach park, hardstanding, access ways, part of slipway.
Temporary works area and access to works
Work Nos. 1A, 1B and 2
District of Thanet
No. 12. Hardstanding providing site for ice cream van.
Temporary works area and access to works
Work Nos. 1A, 1B and 2

---
Source: https://www.legislation.gov.uk/uksi/2005/1137/schedule/3 (the official version)
Page: https://openlegislation.uk/margate-pier-turner-centre-order-2005/schedule-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.