# The Maryport Harbour Revision Order 2007, Paragraph 7


(1) Before beginning to construct any specified work, the Authority shall submit to the Agency plans of the work and such further particulars available to them as the Agency may reasonably require.
(2) Without prejudice to sub-paragraph (1), the Authority shall ensure that any of their contractors shall provide the Agency with all necessary hydraulic information in order to identify and quantify any effects of accumulation or erosion or alteration of the tidal flow or littoral drift which are likely to be caused by any specified work and such information shall be accompanied by an appropriate assessment of that information and of any remedial measures which may be reasonably necessary having regard to any such likely effects.
(3) Any specified work shall not be constructed except in accordance with such plans as may be approved in writing by the Agency or settled in accordance with paragraph 24.
(4) Any approval of the Agency required under this paragraph—
(a) shall not be unreasonably withheld;
(b) shall be deemed to have been given if it is neither given nor refused in writing (and in the case of refusal, with a statement of the grounds for refusal) within two months of the submission of plans for approval;
(c) may be given subject to such reasonable requirements as the Agency may impose for the protection of any drainage work or fishery or water resources, for the prevention of flooding and water pollution and in the discharge of its environmental and recreational duties.

---
Source: https://www.legislation.gov.uk/uksi/2007/3463/schedule/4/paragraph/7 (the official version)
Page: https://openlegislation.uk/maryport-harbour-revision-order-2007/schedule-4/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.