# The Meaford Gas Fired Generating Station Order 2016, Article 33: Certification of plans etc.

Extent: E+W+S

(1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of—
(a) the book of reference;
(b) the land plan;
(c) the works plans;
(d) the access rights of way plan;
(e) the environmental statement;
(f) the design and access statement;
(g) the illustrative landscaping plan;
(h) the illustrative foul and surface water drainage plan; and
(i) the illustrative cross sections drawing,
for certification that they are true copies of the documents referred to in this Order.
(2) A plan or document so certified is admissible in any proceedings as evidence of the contents of the document of which it is a copy.

---
Source: https://www.legislation.gov.uk/uksi/2016/779/article/33 (the official version)
Page: https://openlegislation.uk/meaford-gas-fired-generating-station-order-2016/article-33
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.