# The Meaford Gas Fired Generating Station Order 2016, Paragraph 17: Highway works

Extent: E+W+S

(1) For any highway work in a street for which the highway authority is the street authority, prior to the carrying out of any such work authorised pursuant to article 4 (maintenance of authorised development), article 10 (power to alter layout, etc. of streets) or article 11 (street works) of this Order, the undertaker must submit all necessary technical specifications required for that work for the prior approval of the highway authority.
(2) The highway work must be carried out in accordance with the approved technical specification.

---
Source: https://www.legislation.gov.uk/uksi/2016/779/schedule/2/paragraph/17 (the official version)
Page: https://openlegislation.uk/meaford-gas-fired-generating-station-order-2016/schedule-2/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.