# The Meaford Gas Fired Generating Station Order 2016, Paragraph 49: Vehicles, plant and machinery

Extent: E+W+S

The undertaker must not use any land or property of the Trust forming part of the waterway for the passage or siting of vehicles, plant or machinery employed in the construction of the specified works other than—
(a) with the consent in writing of the engineer whose consent must not be unreasonably withheld or delayed; and
(b) subject to compliance with such reasonable requirements as the engineer may from time to time specify—
(i) for the prevention of detriment; or
(ii) in order to avoid or reduce any inconvenience to the Trust, its officers and agents and all other persons lawfully on such land or property,
but nothing in this paragraph applies in relation to anything done in accordance with any approval given by the Trust under paragraph 53 (design of works).

---
Source: https://www.legislation.gov.uk/uksi/2016/779/schedule/7/paragraph/49 (the official version)
Page: https://openlegislation.uk/meaford-gas-fired-generating-station-order-2016/schedule-7/paragraph-49
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.