(1)

The Medworth Energy from Waste Combined Heat and Power Facility Order 2024 is corrected as set out in the table in Schedule 1 (corrections) to the Order, in which—

(a)

column 1 sets out where the correction is to be made;

(b)

column 2 sets out how the correction is to be made; and

(c)

column 3 sets out the text which is to be substituted, inserted or omitted.

(2)

Part 4 of Schedule 11 to the Medworth Energy from Waste Combined Heat and Power Facility Order 2024 (provisions for the protection of Eastern Power Networks) is omitted and is replaced with the provisions set out in Schedule 2 to this Order.