# The Medworth Energy from Waste Combined Heat and Power Facility Order 2024, Paragraph 112

Extent: E+W+S

The undertaker must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 42 (certification of plans etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail in a format specified by Network Rail.

---
Source: https://www.legislation.gov.uk/uksi/2024/230/schedule/11/paragraph/112 (the official version)
Page: https://openlegislation.uk/medworth-energy-from-waste-combined-heat-and-power-facility-order-2024/schedule-11/paragraph-112
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.