If any damage to any highway or any property of Cambridgeshire County Council on or under any highway is caused by, or results from, the construction of any work authorised by this Order or any act or omission of the undertaker, its contractors, agents or employees whilst engaged upon such work, the undertaker must, in the case of damage to a highway, make good such damage to the reasonable satisfaction of Cambridgeshire County Council and, where the undertaker does not make good, or in the case of damage to property of Cambridgeshire County Council, the undertaker must pay reasonable compensation to Cambridgeshire County Council for such damage.

---
Source: https://www.legislation.gov.uk/uksi/2024/230/schedule/11/paragraph/118 (the official version)
Page: https://openlegislation.uk/medworth-energy-from-waste-combined-heat-and-power-facility-order-2024/schedule-11/paragraph-118
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.