{
  "url": "https://openlegislation.uk/medworth-energy-from-waste-combined-heat-and-power-facility-order-2024/schedule-11/paragraph-120",
  "json_url": "https://openlegislation.uk/medworth-energy-from-waste-combined-heat-and-power-facility-order-2024/schedule-11/paragraph-120.json",
  "legislation": "uksi/2024/230",
  "legislation_title": "The Medworth Energy from Waste Combined Heat and Power Facility Order 2024",
  "legislation_url": "https://openlegislation.uk/medworth-energy-from-waste-combined-heat-and-power-facility-order-2024",
  "path": "schedule/11/paragraph/120",
  "kind": "paragraph",
  "number": "120",
  "heading": null,
  "text": "Cambridgeshire County Council must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which paragraph 118 applies. If requested to do so by the undertaker, Cambridgeshire County Council must provide an explanation of how the claim has been minimised. The undertaker is only liable under paragraph 118 for claims reasonably incurred by Cambridgeshire County Council.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 11 para. 120 in force at 13.3.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/230/schedule/11/paragraph/120",
    "retrieved_at": "2026-10-28T21:34:06.934543+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}