Extent: E+W+S

Cambridgeshire County Council must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which paragraph 118 applies. If requested to do so by the undertaker, Cambridgeshire County Council must provide an explanation of how the claim has been minimised. The undertaker is only liable under paragraph 118 for claims reasonably incurred by Cambridgeshire County Council.

---