# The Medworth Energy from Waste Combined Heat and Power Facility Order 2024, Paragraph 21: Protective works to buildings

Extent: E+W+S

The undertaker must exercise the powers conferred by article 20 (protective works to buildings) so as not to obstruct or render less convenient the access to any apparatus without the written consent of Cadent (such consent not to be unreasonably withheld or delayed).

---