# The Medworth Energy from Waste Combined Heat and Power Facility Order 2024, Paragraph 47: General

Extent: E+W+S

Notwithstanding the provisions of this Order, no works in carrying out, maintaining or diverting the authorised development may be carried out under the strategic road network at a distance within 4 metres of the lowest point of the ground.

---
Source: https://www.legislation.gov.uk/uksi/2024/230/schedule/11/paragraph/47 (the official version)
Page: https://openlegislation.uk/medworth-energy-from-waste-combined-heat-and-power-facility-order-2024/schedule-11/paragraph-47
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.