# The Medworth Energy from Waste Combined Heat and Power Facility Order 2024, Paragraph 67

Extent: E+W+S

(1) Before beginning to construct any specified work, the undertaker must submit to the Board plans of the specified work, evidence to support said plans and any such further particulars available to it as the Board may within 28 days of the submission of the plans (or such other time period as may be agreed between the Board and the undertaker) reasonably require (or submission of further particulars if required by the Board).
(2) Not Used.
(3) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the Board or determined under paragraph 76.
(4) Any approval of the Board required under this paragraph—
(a) must not be unreasonably withheld or delayed;
(b) is deemed to have been given if it is neither given nor refused within 2 months of the submission of the plans for approval (or the submission of further particulars if applicable) or, in the case of a refusal, if it is not accompanied by a statement of the grounds of refusal; and
(c) may be given subject to such reasonable requirements and conditions as the Board may consider appropriate.
(5) The Board must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (4)(b).

---
Source: https://www.legislation.gov.uk/uksi/2024/230/schedule/11/paragraph/67 (the official version)
Page: https://openlegislation.uk/medworth-energy-from-waste-combined-heat-and-power-facility-order-2024/schedule-11/paragraph-67
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.