# The Medworth Energy from Waste Combined Heat and Power Facility Order 2024, Paragraph 1: Time limits

Extent: E+W+S

The authorised development must not commence after the expiration of five years beginning with the date on which this Order comes into force.

---
Source: https://www.legislation.gov.uk/uksi/2024/230/schedule/2/paragraph/1 (the official version)
Page: https://openlegislation.uk/medworth-energy-from-waste-combined-heat-and-power-facility-order-2024/schedule-2/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.