# The Medworth Energy from Waste Combined Heat and Power Facility Order 2024, Paragraph 15: Operational travel plan

Extent: E+W+S

(1) Prior to the date of final commissioning, an operational travel plan must be submitted to and approved by the relevant planning authority. The operational travel plan must set out measures to encourage staff working at Work No. 1, 1A, 1B, 2A and 2B to use sustainable modes of transport and must be substantially in accordance with the outline operational travel plan.
(2) The operational travel plan must be implemented as approved under sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2024/230/schedule/2/paragraph/15 (the official version)
Page: https://openlegislation.uk/medworth-energy-from-waste-combined-heat-and-power-facility-order-2024/schedule-2/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.