# The Medworth Energy from Waste Combined Heat and Power Facility Order 2024, Paragraph 16: Odour management plan

Extent: E+W+S

(1) Prior to completion of commissioning of any part of Work No. 1, an odour management plan must be submitted to the relevant planning authority for approval. The odour management plan submitted for approval must be substantially in accordance with the outline odour management plan.
(2) The relevant planning authority must consult with the Environment Agency before approving the odour management plan.
(3) The odour management plan must be implemented as approved under sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2024/230/schedule/2/paragraph/16 (the official version)