# The Medworth Energy from Waste Combined Heat and Power Facility Order 2024, Paragraph 20: Notice of start of commissioning and notice of date of final commissioning

Extent: E+W+S

(1) Notice of the commencement of commissioning of Work No. 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is commenced.
(2) Notice of the completion of commissioning of Work No. 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is completed.

---
Source: https://www.legislation.gov.uk/uksi/2024/230/schedule/2/paragraph/20 (the official version)
Page: https://openlegislation.uk/medworth-energy-from-waste-combined-heat-and-power-facility-order-2024/schedule-2/paragraph-20