# The Medworth Energy from Waste Combined Heat and Power Facility Order 2024, Paragraph 3: Parameters of authorised development

Extent: E+W+S

The elements of the authorised development listed in column (1) of Table 11 in Schedule 14 (maximum and minimum design parameters) must not exceed the maximum and minimum dimensions and levels set out in relation to that element in columns (3) to (6) of that table.

---
Source: https://www.legislation.gov.uk/uksi/2024/230/schedule/2/paragraph/3 (the official version)
Page: https://openlegislation.uk/medworth-energy-from-waste-combined-heat-and-power-facility-order-2024/schedule-2/paragraph-3/enacted
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.