# The Merchant Shipping and Fishing Vessels (Health and Safety at Work) (Work at Height) Regulations 2010, Paragraph 9

Extent: E+W+S+N.I.

Scaffolding decks shall be assembled in such a way that their components are prevented from moving inadvertently during work at height.

---
Source: https://www.legislation.gov.uk/uksi/2010/332/schedule/2/paragraph/9 (the official version)
Page: https://openlegislation.uk/merchant-shipping-and-fishing-vessels-health-and-safety-at-work-work-at-height-regulations-2010/schedule-2/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.