Paragraph 6
Before the commencement of the initial construction of any part of the specified works and again following completion of the specified works Merseytravel shall bear the reasonable cost of the carrying out by a qualified engineer (the “engineer”), to be approved by the Board and Merseytravel, of surveys (“the surveys”) of so much of the waterway and of any land and existing works of Merseytravel which may provide support for the waterway as will or may be affected by the specified works.
For the purposes of the surveys Merseytravel shall—
on being given reasonable notice (save in case of emergency, when immediate access shall be afforded) afford reasonable facilities to the engineer for access to the site of the specified works and to any land and existing works of Merseytravel which may provide support for the waterway as will or may be affected by the specified works; and
supply the engineer as soon as reasonably practicable with all such information as he may reasonably require with regard to such existing works of Merseytravel and to the specified works or the method of construction thereof.
The reasonable costs of the surveys shall include the costs of any dewatering or reduction of the water level of any part of the waterway (where reasonably required) which may be effected to facilitate the carrying out of the surveys and the provisions of this Schedule shall apply with all necessary modifications to any such dewatering or reduction in the water level as though the same were specified works.
Copies of the surveys shall be provided to both the Board and Merseytravel.