  "heading": "Test loads",
  "text": "(1) Every repaired meter shall be tested at each of the loads specified in Table 2.\n(2) All new meters shall be calibrated and tested at a sufficient number of load points so as to ensure that meter errors are not greater than the limits specified in paragraph 9.\n(3) A test will also be carried out on new meters for starting in accordance with Test No 7 of Table 2.\n(4) The ratio accuracy shall be determined for voltage transformers that are intended for use with meters but are not tested with a meter.\n(5) Current transformers intended for use with meters but not tested with a meter shall be tested from 5% to 100% of rated current.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/1990/792/schedule/1/paragraph/6",
    "retrieved_at": "2026-10-29T15:22:08.525435+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}