(1) The following tests shall not be carried out until the voltage circuits of meters under test and the voltage circuits of working standard integrating meters have been energised for a period of one hour or half an hour if a current of not less than either 10 per cent. of basic current or 5 per cent. of marked current is applied to the current circuits of the meters, provided that the non-registration and starting current tests may be carried out during the pre-heating period.
(2) Sub-paragraph (1) shall not apply to a meter which the examiner is satisfied is capable of full operation as soon as it is energised.

---