(1)
Number of land shown on the land plans
(2)
Purposes for which temporary possession may be taken
2, 14
Construction of permanent works on that land to tie in different levels, working site and access during construction.
3, 4
Construction access and working site. Construction of permanent bridge strengthening works.
5
Construction compound.
7
Installation of permanent traffic signalling apparatus, construction of permanent works to realign highway and working site.
12
Construction of permanent works on that land to alter private road and tie in different levels and access during construction.
13
Construction of permanent works on that land to alter private road, provide a turning head and tie in different levels and access during construction.

---
Source: https://www.legislation.gov.uk/uksi/2019/882/schedule/3 (the official version)
Page: https://openlegislation.uk/midland-metro-birmingham-city-centre-extension-etc-edgbaston-extension-land-acquisition-order-2019/schedule-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.