# The Millbrook Gas Fired Generating Station Order 2019, Introduction: Introductory text

Extent: E+W+S

Infrastructure Planning
Made 13th March 2019
Coming into force 3rd April 2019
An application under section 37 (applications for orders granting development consent) of the Planning Act 2008 (the “2008 Act”) has been made to the Secretary of State for an order granting development consent.
The application has been examined by a single appointed person appointed by the Secretary of State pursuant to Chapter 3 (the single appointed person procedure) of Part 6 of the 2008 Act and carried out in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010 . The single appointed person has submitted a report and recommendation to the Secretary of State under section 83 (single appointed person to examine and report on application) of the 2008 Act .
The Secretary of State has considered the report and recommendation of the Examining Authority, has taken into account the environmental information in accordance with regulation 3 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2009 and has had regard to the documents and matters referred to in section 104(2) (decisions in cases where national policy statement has effect) of the 2008 Act.
The Secretary of State, having decided the application, has determined to make an order giving effect to the proposals comprised in the application on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
In accordance with section 127 (statutory undertakers' land) of the 2008 Act , the Secretary of State has applied the relevant tests and is satisfied that they have been met.
Accordingly, the Secretary of State, in exercise of the powers in sections 114 (grant or refusal of development consent order), 115 (development for which development consent may be granted), and 120 (what may be included in order granting development consent) of the 2008 Act, makes the following Order—

---
Source: https://www.legislation.gov.uk/uksi/2019/578/introduction (the official version)
Page: https://openlegislation.uk/millbrook-gas-fired-generating-station-order-2019/introduction
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.