Work No. 4A development comprising a gas pipeline including—
(a) a new underground gas pipeline connection and telemetry cabling, approximately 1.8km in length connecting Work No. 1B to Work No. 3A;
(b) pipeline field marker posts and cathodic protection test/ transformer rectifier unit;
(c) below ground drainage works;
(d) works required in order to protect existing utilities infrastructure;
(e) tree and hedge removal;
(f) landscaping including tree planting, temporary and permanent fencing and other boundary treatments and ecological mitigation; and
(g) creation of construction access from Houghton Lane,

---