# The Millbrook Gas Fired Generating Station Order 2019, Paragraph


Work No. 1D development comprising a generating station including—
(a) security infrastructure, including cameras, perimeter fencing and a gatehouse;
(b) site lighting infrastructure, including perimeter lighting columns;
(c) internal roadways, car parking, pedestrian network, cycle parking, hardstanding and water treatment trailers;
(d) a maintenance compound including hardstanding and welfare and administration facilities;
(e) site drainage and waste management infrastructure, including relocation of existing infrastructure as required;
(f) electricity, water, wastewater and telecommunications and other services including high voltage and low voltage cabling, equipment and controls and associated telemetry and electrical protection auxiliary cabling;
(g) landscaping including tree planting, temporary and permanent fencing and other boundary treatments and ecological mitigation; and
(h) other ancillary equipment.

---
Source: https://www.legislation.gov.uk/uksi/2019/578/schedule/1/paragraph/wrapper6n1 (the official version)
Page: https://openlegislation.uk/millbrook-gas-fired-generating-station-order-2019/schedule-1/paragraph-wrapper6n1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.