Work No. 3A development comprising gas infrastructure including—
(a) an above ground installation (also referred to as a minimum offtake connection compound) containing—
(i) a minimum offtake connection comprising remotely operable valves, control and instrumentation kiosks and electrical supply kiosks;
(ii) a pipeline inspection gauge (PIG) facility, comprising a PIG launching facility, emergency control valves, isolation valves, control and instrumentation kiosks, and electricity supply kiosks;
(b) security infrastructure, including cameras, lighting (including perimeter lighting columns) and perimeter fencing;
(c) site drainage and waste management infrastructure;
(d) electricity and telecommunications connections and other services;
(e) below ground sacrificial anode pit; and
(f) landscaping including tree planting, temporary and permanent fencing and other boundary treatments and ecological mitigation,

---
Source: https://www.legislation.gov.uk/uksi/2019/578/schedule/1/paragraph/wrapper9n1 (the official version)
Page: https://openlegislation.uk/millbrook-gas-fired-generating-station-order-2019/schedule-1/paragraph-wrapper9n1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.