# The Millbrook Gas Fired Generating Station Order 2019, Part 1: THOSE PARTS OF THE ACCESSES TO BE MAINTAINED AT THE PUBLIC EXPENSE

Extent: E+W+S

Table 6
(1)Location
(2)Street
(3)Description of relevant part of access
Central Bedfordshire Council
Green Lane
The signage and markings installed in the area hatched blue between points A and B as shown on the rights of way, streets and access plan.
Bedford Borough Council
Green Lane
The signage and markings installed in the area hatched magenta between points A and B as shown on the rights of way, streets and access plan.
Central Bedfordshire Council
Houghton Lane
The upgraded access constituting part of numbered work 3B and shown on the rights of way, streets and access plan hatched blue between points OO and PP.

---
Source: https://www.legislation.gov.uk/uksi/2019/578/schedule/5/part/1 (the official version)
Page: https://openlegislation.uk/millbrook-gas-fired-generating-station-order-2019/schedule-5/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.