# The Millport Harbour Revision Order 2023, Article 9: Period for completion of the works


(1) Subject to paragraph (2), if the works are not substantially completed within 3 years from the coming into force of this Order or such extended time as the Ministers may on the application of the Council allow by consent in writing, then on the expiration of that period or such extended time (as the case may be) the powers granted by this Order to the Council for constructing and maintaining the works shall cease, except as to those works as are at that time substantially commenced.
(2) Nothing in paragraph (1) shall apply to any works carried out under article 4 (power to renew) or article 6 (subsidiary works).
(3) A consent given under paragraph (1) may be given unconditionally or subject to terms and conditions.
(4) As soon as reasonably practicable after a consent is given under paragraph (1) the Council shall arrange for a notice to be published in the Edinburgh Gazette and in a local newspaper in the area where the harbour is situated and the notice shall contain a concise summary of that consent.
(5) During the period of one month beginning with the date on which any notice is published in the Edinburgh Gazette and a local newspaper under paragraph (4), a copy of the consent referred to in that notice shall be kept by the Council at the office of the Chief Executive, The North Ayrshire Council, Cunninghame House, Irvine KA12 8EE and shall be open to public inspection without payment or be made available electronically on request.

---
Source: https://www.legislation.gov.uk/ssi/2023/167/article/9 (the official version)
Page: https://openlegislation.uk/millport-harbour-revision-order-2023/article-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.